L-G: Ahead of G20, Pragati Maidan tunnel in Delhi caused national embarrassment

PWD had also pulled up L&T for not completing the underpass number 5 on Bhairon Marg, located below railway tracks

pragati maidanThe Pragati Maidan tunnel project, readied in the nick of time for the G20 Summit, has been facing issues like seepage, large cracks on the surface, and walls to poor drainage (Express File Photo)
Written by: Gayathri Mani
3 min readNew DelhiOct 8, 2025 05:15 AM IST First published on: Oct 8, 2025 at 05:15 AM IST

As he ordered a probe into the construction of Barapullah Phase III flyover project, Lieutenant Governor V K Saxena on Tuesday said that the Pragati Maidan tunnel near Bharat Mandapam “caused national embarrassment ahead of the G20 Summit”, considering it was constructed by the “same construction agency”, Larsen & Toubro (L&T) Limited.

In an internal note to the Chief Secretary, the L-G criticised L&T, the construction agency involved in both the projects.

Advertisement

“The extraordinary delay in this project (Barapullah Phase-III flyover) has raised some fundamental policy issues which must be addressed: Whether large projects of this nature should have arbitration clauses embedding in them which provides incentive to contractors for making exorbitant claims as has been seen in other matters as well, even when the contractor is at fault?” Saxena said.