Bhalswa landfill to be cleared by next March: CM Kejriwal

The Chief Minister said that in 2019, the landfill site had around 80 lakh tonnes of waste dumped there, of which, around 30 lakh tonnes has been removed by biomining so far, leaving 50 lakh tonnes.

Kejriwal visited the landfill on Thursday with minister Saurabh Bharadwaj. PTIKejriwal visited the landfill on Thursday with minister Saurabh Bharadwaj. PTI

Inspecting the Bhalswa landfill on Thursday, Chief Minister Arvind Kejriwal said that the landfill, one of three landfill sites in the capital, will be cleared by March 2024.

Kejriwal visited the landfill on Thursday along with Urban Development Minister Saurabh Bharadwaj, Mayor Shelly Oberoi, and Deputy Mayor Aaley Mohammad Iqbal.

The Chief Minister said that in 2019, the landfill site had around 80 lakh tonnes of waste dumped there, of which, around 30 lakh tonnes has been removed by biomining so far, leaving 50 lakh tonnes. Since 2019, when the quantity of waste at the site was estimated, 24 lakh tonnes of fresh waste has been dumped at the landfill, going by a communication from the CMO.

Of the waste that is still at the site, another 30 lakh tonnes will be cleared by December this year and all the legacy waste at the site will be cleared by March 2024, said the Chief Minister. By the end of the month, 12,000 tonnes of waste will be cleared from the site every day, an increase from what was 9,000 tonnes that was processed Wednesday.

Legacy or old waste at the landfills in the city is being biomined to clear the sites. According to a drone survey conducted last year, the Bhalswa landfill occupies 78.47 acres and dumping of waste at Bhalswa began in 1994. After an NGT order in 2019, the biomining of waste began at the landfills in Delhi.

According to a status report submitted by Delhi Pollution Control Committee at the National Green Tribunal last month, the city generates around 11,332 TPD (tonnes per day) of municipal solid waste, and of this, 4,360 TPD is not processed, which means that this waste ends up at the landfills. A total of 11 waste processing facilities are proposed in the city to deal with this shortfall, including expansion of the existing waste-to-energy plant at Okhla, and two new waste-to-energy plants — one each at Ghazipur and Narela-Bawana. These facilities will have a combined capacity of 6,462 TPD.