House panel flags variance in Railways’ line doubling project data: ‘Nearly 74% fund spent but physical progress is just 39%?’
The panel said that the railways should exercise due diligence in identifying and addressing obstacles to ensure seamless project execution
The target for railway line doubling in the upcoming financial year 2025-26 is 2,600 km at the cost of Rs 32,000 crore (Archives) The Parliamentary Standing Committee on Railways has flagged the disparity over the total expenditure and physical progress of the works being done under the doubling of railway lines, one of the key projects of the railways to increase the capacity and remove traffic bottlenecks.
The committee said that while the financial utilisation or the total amount spent on the doubling of railway lines up to December 2024 (for financial year 2024-25) was 74 per cent of the budget, the physical achievement was merely 39 per cent of the target.
“Regarding doubling projects, the committee found that against a target of 2,900 km, only 1,134 km (39.10 per cent) was achieved during 2024-25 (up to December 2024). While the Budget Estimate (BE) for doubling was Rs 29,312 crore, it was revised upward at the Revised Estimate (RE) stage to Rs 31,036.86 crore, with actual utilisation reaching Rs 22,918.57 crore (73.85 per cent of RE) (up to December 2024)… The Committee would like to be apprised of the factors leading to this disparity,” said the Parliamentary Standing Committee on Railways in its report on Demands for Grants (2025-26) of the Ministry of Railways, which was presented in Lok Sabha on March 10, 2025.

